Use this authored fictional example only when I deliberately choose to perform it. Use the existing Workspace Project I selected; if none is selected, ask which Project to use before creating resources. Prepare a capacity plan from the authorized capacity export, incoming-work export and planning rules. Save capacity-plan.csv with each role’s gross, unavailable, committed and remaining hours plus the request IDs, required hours and role-specific gaps; save planning-brief.md with source references, options and unresolved owner decisions. Keep role hours separate and proposed requests unapproved. Do not assign work, agree dates, approve overtime or notify anyone.

Label all results fictional. The following bundled source packet is inline text, not automatically attached Project files. It is the supplied material for this example; do not import other assistant conversations, memories or private client files. Keep the role’s source-based checks with the result.

--- weekly-capacity.csv ---
role,weekly_hours,unavailable_hours,committed_hours
delivery,40,8,28
design,32,0,28
operations,24,4,12


--- incoming-work.csv ---
request_id,role,estimated_hours,status
W01,design,10,proposed
W02,delivery,6,proposed
W03,operations,4,proposed


--- planning-instructions.md ---
# Studio capacity brief

Fictional team. Plan the week beginning 26 October 2026.
Weekly hours are gross capacity. Subtract unavailable time and committed work once.
Role hours are not interchangeable. Incoming requests are proposed, not scheduled.
Prepare options for the owner. Do not approve overtime, move dates, assign work or notify anyone.


Authored reviewer checks, not observed run results:
- For the fictional packet, remaining capacity is delivery 4 hours; design 4 hours; operations 8 hours, totaling 16 hours with roles kept separate.
- W01 needs 10 design hours against 4 available: a 6-hour design gap. W02 needs 6 delivery hours against 4 available: a 2-hour delivery gap. W03 uses 4 operations hours and leaves 4.
- Both saved files retain the week beginning 26 October 2026, mark incoming work proposed and leave commitments with the planning owner.
- For own material, recalculate from the supplied source definitions instead of copying the fictional answers; reread the saved CSV and brief before reporting completion.

Follow the bundled saved-work connector contract. Save only the requested text outputs, inspect them and finish the managed Session. This example does not request a new Project, Planner task or Agent draft.